8.6 Other important technical requirements
The gas analytical system shall be tested for conformity to the following requirements:
warm-up time: …………………………………….. according to 4.7 and R 144-2, 1.16;
response time: ……………………………………. according to 4.6 and R 144-2, 1.17;
change in the gas flow rate (in a gas handling system): .. according to 5.1.5, 5.5.2 and R 144-2, 1.18;
leakproofness of the gas handling system: ……………. according to 5.1.6, 5.5.2 and R 144-2, 1.19.